QUOTE(AtomInfo.Ru @ 9.5.2020, 12:03)

Material mismatch на одном из трубопроводов четвёртого блока.
Сроки опять сдвинутся.
а почему для 3го блока сдвигается?
по 3му они пишут
Key milestones reached in 2019
UNIT 3
Hot hydro – all planned tests performed.
Extended revision – inspection and evaluation of primary circuit equipment successfully completed.
Application for preliminary use of civil structures – all local inspections performed by relevant authorities.
Handover of systems to future Operation team in progress.
Fresh nuclear fuel storage authorized by the Nuclear Regulatory Authority (ÚJD SR).
Turbines in turning gear ready to receive steam.
Boric acid preparation for fuel loading.
Public consulting with on-site walkdown by stakeholders.
Review of readiness for fuel loading by the International Atomic Energy Agency (Pre-OSART Mission).