QUOTE(AtomInfo.Ru @ 31.8.2016, 9:45)

Сами индийцы вот так отвечают:
Я ожидал комментарий от "причастных", на ранее указанную ссылку, в которой, в частности :
Kudankulam nuclear power plant (KKNPP-1):
The AERB had prepared a list 45 individual tests in C-Phase. The attempt to clear the final test in
which the reactor had to be operated for ‘non-stop 100 days on 100% full power (100%FP)’
began on 05 May 2014. During the 825 days between 05 May 2014 and 06 August 2016, the
reactor was on 100%FP for 217 days, not Non-stop, but in 13 instalments. The maximum it ran
non-stop was 45 days in January-March 2015. All the 11 attempts so far ended up either in
emergency shutdowns or abrupt drop in output and the last attempt began on 19 July 2016.
Т.е. 100 дней непрерывно на 100% KKNPP-1, так и не проработал еще . . .